How to Read a TxDOT Bid Tab: A Field Guide for Civil Contractors

Every year, TxDOT puts out hundreds of millions in civil construction work across Texas. If you're a small civil crew doing excavation, grading, drainage, or paving — that's your market.

But the first time you open a TxDOT Invitation to Bid, it can look like a different language. Hundreds of line items, four-digit item codes, units you don't recognize, and spec sections you've never seen.

This guide breaks it down. By the end, you'll know how to read any TxDOT bid schedule and price it without missing anything.

What is a TxDOT bid tab?

A "bid tab" (bid tabulation) is the document where you enter your unit prices for a TxDOT project. TxDOT publishes it before the bid opening, you fill in your prices, and they evaluate all bids based on the total.

After bid opening, TxDOT publishes the completed bid tab showing every contractor's prices — which is where you can see what the low bidder priced. That historical data is gold.

The TxDOT bid tab has three main components:

  1. Item number — a 9-digit code from TxDOT's Standard Specifications
  2. Description — what the work is
  3. Quantity and unit — how much of it you're pricing

Your job: fill in a unit price for each line item.

Understanding TxDOT item codes

TxDOT uses a standardized item coding system. Every item has a 9-digit code in this format: XXX-X-XXXXX

The first three digits identify the item category. Here are the most common ones for civil work:

Code RangeCategory
100-199Preparing ROW, earthwork, subgrade
200-299Flexible base, subbase, lime/cement stabilization
300-399Flexible pavement (HMAC, surface treatments)
400-499Rigid pavement (concrete)
500-599Structures (culverts, retaining walls, bridges)
600-699Traffic control, signs, markings
900-999Miscellaneous items

If you see item 132-6-00001, you're in the earthwork category. Item 247-7-00001 is flexible base. Item 432-D-04011 is reinforced concrete culvert.

Common TxDOT units explained

TxDOT uses consistent unit abbreviations across all projects:

UnitMeans
CYCubic yard (earthwork, concrete, aggregate)
LFLinear foot (pipe, curb, fencing)
SYSquare yard (pavement, surface treatment)
SFSquare foot (smaller areas, flatwork)
TONTons (HMAC, aggregate base)
EAEach (structures, inlets, signs, fixtures)
STAStation (100 linear feet — used for clearing, striping)
LSLump sum (mobilization, traffic control, erosion control)
GALGallons (tack coat, herbicide)

Reading the bid schedule line by line

When you're reviewing a TxDOT bid schedule, here's your checklist:

1. Match item codes to your scope. Know which items are yours to price. On a sitework bid you might price earthwork (100s) and drainage (500s) but not pavement (300-400s) if that's a subcontract.

2. Check the quantities against the plans. TxDOT engineers make mistakes. Earthwork quantities especially can be off. If you have access to the plans, verify takeoff before locking in your price.

3. Flag lump sum items. Mobilization, traffic control, and erosion control are often LS — and what's included can vary. Check the specification section before pricing LS items.

4. Look for alternates. Some bid schedules have base bid + alternate bid sections. Price them separately.

5. Check units carefully. Is it CY or TON? SY or SF? Getting units wrong by a factor of 9 (SY vs SF) will crater your bid.

Where to find TxDOT bid documents

TxDOT posts all active bids on their LetConnect system. The bid schedule PDF is in the proposal document, labeled "Bid Proposal" or "Bid Tabulation."

TxDOT publishes results after each letting date — you can see every contractor's prices. That historical data is invaluable for calibrating your unit prices.

How to price TxDOT bids faster

The standard approach: transcribe the bid schedule from the PDF into Excel, then price each item. The problem is a typical TxDOT road project has 100-200+ line items — that's 2-3 hours of typing before you've touched pricing.

CivBid reads the TxDOT bid tab PDF and extracts every line item, quantity, and unit automatically. You review the extraction, fix any errors, then price from your catalog. If you've priced Roadway Excavation (110-1-00010) before, CivBid shows your last unit price.

Try it with your next TxDOT proposal — upload the PDF at civ.bid/try. No signup required.

The TxDOT bid tab checklist

Before you submit:

  • Every line item has a unit price (TxDOT disqualifies incomplete bids)
  • Lump sum prices include everything in the spec
  • Quantities spot-checked against plans for major earthwork items
  • Base bid and alternate bid totals are separate
  • Bid bond attached (required for most TxDOT projects)
  • Submitted before the letting date deadline (no extensions)

TxDOT lettings happen on a schedule — typically the first and third Tuesday of each month. Missing the deadline means your bid is rejected, no exceptions.

Ready to try it?